Project Completion Dossier — Homs, Syria Project Completion Dossier Homs 400/230 kV Substation Project Completion Dossier Client / Employer Ministry of Electricity — SAR Contractor (EPC) ICC Energy DWC-LLC Site Homs Governorate Homs Governorate now has a fully commissioned 400/230 kV transformation substation, engineered, procured, and constructed by ICC Energy DWC-LLC under a full EPC contract with Syria's Ministry of Electricity. The project moved from award to final commissioning in exactly 24 months — the schedule the contract called for. The Ministry of Electricity's Public Establishment for Electricity Transmission and Distribution awarded ICC Energy the design-and-build contract for the Homs substation in May 2020, at a value close to 32 billion Syrian Pounds. The scope covered every phase from detailed engineering through procurement, construction, and final handover. "The works were executed and duly accepted after passing all ...
Welcome to the Homs Energy Blog — documenting ICC Energy DWC-LLC's delivery of the 400/230 kV transformation substation in Homs Governorate, Syria. Awarded by the Ministry of Electricity in May 2020, this full EPC project reached final commissioning in May 2022 after 24 months of design, procurement, and construction. The substation serves as a critical link in Syria's national transmission grid, providing reliable power to homes, hospitals, and industry across the governorate. This blog covers